Cityline Sunnyvale Project

Cityline Sunnyvale on Facebook


1 day ago

Cityline Sunnyvale Construction

The Murphy Avenue extension has been completed! Additionally, we have re-striped the garage and planted landscaping. Access has been fully restored, come on down and check it out!

You can also see work progressing on the Whole Foods and AMC Theater in the background.
... See MoreSee Less

The Murphy Avenue extension has been completed! Additionally, we have re-striped the garage and planted landscaping. Access has been fully restored, come on down and check it out!

You can also see work progressing on the Whole Foods and AMC Theater in the background.
http://citylinesunnyvaleconstruction.com/project-updates/

The latest Construction updates through 4/25/18 are now available at www.citylinesunnyvlaeconstruciton.com


Project Map


Click on image to enlarge

 

Contacts

Disturbance Coordinator
Ron Schneider
DEVCON Construction
408-590-8762

Development Teams

Hunter/Storm
Commercial Developer
408-255-4100
Sares Regis Group of Northern California
Residential Developer
650-378-2800

Commercial Leasing Contacts

James Chung
Managing Principal, West Region Retail
CA License #01408190
Direct: 408-436-3630
james.chung@cushwake.com
Nicole Lyon
Associate
CA License #01975898
Direct: 925-627-2485
nicole.lyon@cushwake.com

Project Progress Update

New Murphy Avenue roadway graded and placed compacted AB section. Preparing for paving. View/Download the current project progress update here. … [Read more]

3/08/2018

Anticipated infrastructure improvements will occur at the following locations through 3/14/2018. Saturday work will take place 3/10/18 between the approved construciton hours of 8 am-5 pm. Work includes the following activities: Traffic … [Read more]

March Update

Infrastructure improvements will occur at the following locations through 3/7/2018. This work includes: Traffic signal work at Mathilda/Washington intersection, including removal of existing wheelchair accesible ramps and placement of new … [Read more]

Infrastructure improvements

2/21/18-2/28/18: Infrastructure improvements will occur at the following locations & include: • Traffic signal work at Mathilda/Washington intersection, including wheelchair-accesible ramp removal • Traffic signal work at … [Read more]

East Iowa

2/16/18: Anticipated infrastructure improvements will occur at the following locations through 2/21/2018. This work will include: Traffic signal work at Mathilda/Washington intersection Traffic signal work at Mathilda/Iowa intersection … [Read more]

McKinley and Taaffe closures

McKinley  and Taaffe closures are expected 2/20 through 2/23. View or Download Road Closures Notification for additional information. … [Read more]

On Wednesday, January 31

On Wednesday, January 31, several downtown property owners will host an open house to discuss their respective proposals to complete a vibrant, walkable downtown with a balanced mix of uses that celebrate Sunnyvale’s character. Download the … [Read more]

November Update

Jan. 4, 2018  Work has begun on the new Murphy St. extension. Not much to look at yet, but the final product will be worth the wait! … [Read more]

December  business update

December  business update  Wednesday, 12/6 @ 9:30am at the Sunnyvale Chamber of Commerce office.  Remember, all downtown businesses remain OPEN DURING CONSTRUCTION of Cityline   … [Read more]