Cityline Sunnyvale Project

Cityline Sunnyvale on Facebook


Join us at the upcoming City Council Study Session at 5:30 on 3/5 at City Hall to hear about Downtown Progress and voice your opinion on what you want to see! ... See MoreSee Less

If you’re interested in learning about what we’re working on for the future phases of CityLine, stop by the planning commission study session at the Library Program Room at 5pm today! ... See MoreSee Less


Project Map


Click on image to enlarge

 

Contacts

Disturbance Coordinator
Ron Schneider
DEVCON Construction
408-590-8762

Development Teams

Hunter/Storm
Commercial Developer
408-255-4100
Sares Regis Group of Northern California
Residential Developer
650-378-2800

Commercial Leasing Contacts

James Chung
Managing Principal, West Region Retail
CA License #01408190
Direct: 408-436-3630
james.chung@cushwake.com
Nicole Lyon
Associate
CA License #01975898
Direct: 925-627-2485
nicole.lyon@cushwake.com

Infrastructure improvements occurring through 4/25/2018

Below are the anticipated infrastructure improvements occurring through 4/25/2018. This work includes the following: Work to be performed Saturday, 4/21/2018: Iowa / Sunnyvale – St. Francis Electric performing infrastructure work demo & place … [Read more]

Anticipated infrastructure improvements

Anticipated infrastructure improvements will occur at the following locations during the through 4/18/2018. This work includes the following: Mathilda Ave.: Washington Ave. center islands pour back, NE corner pour back walkway/ wheelchair … [Read more]

April 11

April 11. 2018: please note upcoming parking lot closures at Cityline Sunnyvale. Download PDF … [Read more]

4/11/18

Anticipated infrastructure improvements will occur at the following locations through 4/11/18. This work will include: Mathilda/Washington intersection: including removal of existing wheelchair accesible ramps and placement of new ramps; NW corner … [Read more]

Last Minute Update for Saturday 3/31 Work

Last Minute Update for Saturday 3/31 Work: Pothole work and infrastructure at the Iowa/Sunnyvale and McKinley/Mathilda Avenue intersections as well as concrete demolition and vacuum truck work. … [Read more]

Anticipated infrastructure improvements

Anticipated infrastructure improvements will occur at the following locations through 4/4/18. Work to include the following: Mathilda/Washington Ave. intersection, including removal of existing wheelchair accesible ramps and placement of new … [Read more]

Anticipated infrastructure improvements

Anticipated infrastructure improvements occurring at the following locations through 3/28/2018. This work includes the following: Mathilda/Washington Ave. intersection, including removal of existing wheelchair accessible ramps and placement of … [Read more]

Saturday March 24

Work to be Performed on Saturday March 24: Mathilda at Iowa – Handicap ramp demo/pour back (Mathilda/Iowa work will be limited to sidewalk only using existing traffic control plan) New Murphy – grading and forming/pouring curbs in front of … [Read more]

Mathilda/Washington

Anticipated infrastructure improvements will occur at the following locations through 3/21/2018. This work includes the following activities: Traffic signal work at Mathilda/Washington intersection, including removal of existing wheelchair … [Read more]

March 17

Work to take place Saturday, March 17. Murphy Ave. North: make up for rain delays. Grading along Murphy Ave. to get conforms ready for the paving scheduled for Monday, 3/19/18. Trucks coming in/out of the parking lot gates, appropriate … [Read more]