Anticipated infrastructure improvements will occur at the following locations during the through 4/18/2018. This work includes the following:
Mathilda Ave.:
- Washington Ave. center islands pour back, NE corner pour back walkway/ wheelchair accesible ramp.
- Iowa St.complete NE -HCR, demo pour back SE HCR, demo pour back center island nosing.
- McKinleyAve. pothole for signal pole foundations.
Iowa St.
- Taaffe: intersection switchover 4/16/18
- Frances: Complete crosswalk open up center turning lane unto Frances.
- S. Murphy Ave. continue crosswalk
Sunnyvale:
- Iowa St: continue signal pole infrastructure
- McKinley: continue East crosswalk.
MurphyAve./Washington:
- Slurry Stripe Block 6 – 4/15 – 18